DC Water’s Fourth Tunnel Boring Machine Journeying Underground for Clean Rivers

October 07, 2013

DC Water’s fourth tunnel boring machine (TBM) is chewing its way under Tingey Street today to create a tunnel to support healthier waters. This work is part of the Tingey Street Diversion Sewer. The 8-foot-diameter TBM was launched from a shaft just east of Nationals Park and is remote-controlled, set on a specified course connecting from 2nd to just beyond 5th Street, SE, running under Tingey Street. The tunnel is part of a massive $2.6 billion environmental program, called the DC Clean Rivers Project, to improve the health of local waterways.

As in many older cities, about one-third of the District has a combined sewer system, meaning that both runoff and sewage are conveyed in the same pipe system. Combined sewer overflows, CSOs, occur during intense rains when the volume exceeds the capacity of the pipes, and some of it must overflow to the nearest water body rather than backing up in homes and streets. Modern engineering avoids this problem with separate pipes for sewage and stormwater. Since the early 1900’s, only separate sewer systems have been installed in the District. DC Water’s plan to significantly reduce CSOs to the Anacostia River is to build massive underground tunnels that will store the combined sewage and runoff during intense rains and then slowly release it when the system has the capacity to treat it.

DC Water General Manager George S. Hawkins, commented, “Evidence of the work for the Clean Rivers Project can be seen across the District, and this tunnel is another step towards our ultimate goal of healthier waterways. When the projects are complete, DC Water will reduce CSOs to the Anacostia by 98 percent and to all of our waterways by 96 percent.”

The Tingey Street tunnel is about 1,200 ft long, has a six-foot-diameter concrete lining and will be able to convey more than 50 million gallons per day of combined sewage to Blue Plains for treatment. It is typical to name tunnel boring machines and this one was ceremoniously named “Go Yard” before being lowered into the launch shaft. It is expected to accomplish its mission and “break through” this week. A larger TBM, the 26-foot-diameter Lady Bird, is currently under the Potomac River, tunneling north for a total of more than 20,000 linear feet. There is also a smaller TBM under M Street, SE, and last year’s tunneling at the 11th Street Bridge on the south side of the Anacostia River was performed by another small TBM.

For more information on the DC Clean Rivers Project, please visit www.dcwater.com/cleanrivers.

Latest News

Picture of frozen water pipes with icicles hanging off of them

With December getting off to a near-record cold start now is the time to act. Winter weather can bring risks like frozen pipes, water main breaks, and other emergencies that can disrupt your water service. Don’t wait for something to happen. DC Water encourages customers to prepare now and know what to do if the unexpected happens.

Worker on side of steep slope

TRAFFIC ADVISORY - CLEAN RIVERS - POTOMAC RIVER TUNNEL PROJECT

DC Water is in the final stretch of its slope stabilization project along Canal Road NW, a critical project that will pave the way for Potomac River Tunnel construction at this site. Beginning, the week of December 15, 2025, one westbound lane of Canal Road will be closed during daytime, off-peak hours on weekdays and Saturdays to hydroseed the slope.

Image of Wendy with EPA Letter

DC Water is reaching out to nearly 25,000 customers this month with important information about the material of their water service lines. These annual notifications are part of DC Water’s ongoing commitment to prevent exposure to lead and remove lead service lines from the District’s drinking water system through the Lead Free DC initiative.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Worker on side of steep slope
Canal Road Slope Stabilization Project Nears End; Off-peak Lane Closure to Replant Slope

TRAFFIC ADVISORY - CLEAN RIVERS - POTOMAC RIVER TUNNEL PROJECT

DC Water is in the final stretch of its slope stabilization project along Canal Road NW, a critical project that will pave the way for Potomac River Tunnel construction at this site. Beginning, the week of December 15, 2025, one westbound lane of Canal Road will be closed during daytime, off-peak hours on weekdays and Saturdays to hydroseed the slope.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.
Upcoming Meeting

Upcoming Events

Customer Service Center Announcement

Payment Plan Incentive: provides a credit back of 40% of the last 3 payments made and in the new fiscal year 50% will be credited. Eligible participants are residential customers who have had an outstanding balance for 60 days or greater and with an outstanding balance of $500 or more.