Media Advisory: DC Water to Hold Ceremonial Blessing for Tunnel Boring Machine "Mary," Signaling Start of Digging for Potomac River Tunnel Project

October 29, 2025
Section of Tunnel Boring Machine Mary being prepared for excavation to begin

Monday, November 3, DC Water will host a ceremonial blessing for Mary, the massive tunnel boring machine (TBM) that will soon begin her underground journey to build part of the Potomac River Tunnel. DC Water CEO and General Manager David L. Gadis will be joined by DC Mayor Muriel Bowser, DC Water Board Chair Dr. Unique N. Morris-Hughes, and other District leaders, to mark this major milestone on the project which will dramatically improve water quality in the District.

Mary will tunnel northward from West Potomac Park, while her sister TBM, Emily, will soon arrive from Germany to dig southward. Together, they will help keep nearly a billion gallons of combined sewage and stormwater overflows from entering the Potomac River in an average year of rain.

WHAT: Blessing Ceremony for Tunnel Boring Machine Mary — Signaling the Start of Digging for the Potomac River Tunnel
WHO: Muriel Bowser, Mayor District of Columbia
David L. Gadis, DC Water Chief Executive Officer & General Manager
Dr. Unique N. Morris-Hughes, DC Water Board Chair 
Moussa Wone, Vice President DC Clean Rivers Project
WHEN: Monday, November 3, 2025, at 11:00 a.m.
WHERE: Potomac River Tunnel Project Site
West Potomac Park
4592 Ohio Dr SW (Ohio Dr & West Potomac Park Dr)
Washington, DC 20551
 

The event entrance is located at Ohio Dr and West Potomac Park Dr. Street parking is available. Please wear closed-toe footwear appropriate for a construction site.

Following the event, attendees will have the opportunity to tour the launch site and view the drop shaft — a 100-foot-deep vertical tunnel where Mary will begin her excavation. This shaft is a key part of the tunnel system that will carry stormwater and sewage to DC Water’s Blue Plains Advanced Wastewater Treatment Plant.

Media interested in attending are encouraged to RSVP by Sunday, November 2 at 5 p.m. to: Sherri Lewis — sherri.lewis@dcwater.com

Latest News

Picture of frozen water pipes with icicles hanging off of them

With December getting off to a near-record cold start now is the time to act. Winter weather can bring risks like frozen pipes, water main breaks, and other emergencies that can disrupt your water service. Don’t wait for something to happen. DC Water encourages customers to prepare now and know what to do if the unexpected happens.

Worker on side of steep slope

TRAFFIC ADVISORY - CLEAN RIVERS - POTOMAC RIVER TUNNEL PROJECT

DC Water is in the final stretch of its slope stabilization project along Canal Road NW, a critical project that will pave the way for Potomac River Tunnel construction at this site. Beginning, the week of December 15, 2025, one westbound lane of Canal Road will be closed during daytime, off-peak hours on weekdays and Saturdays to hydroseed the slope.

Image of Wendy with EPA Letter

DC Water is reaching out to nearly 25,000 customers this month with important information about the material of their water service lines. These annual notifications are part of DC Water’s ongoing commitment to prevent exposure to lead and remove lead service lines from the District’s drinking water system through the Lead Free DC initiative.

Upcoming Meeting

Board of Directors Meeting

April 24, 2023

Monday 9:00 AM

Announcement

Worker on side of steep slope
Canal Road Slope Stabilization Project Nears End; Off-peak Lane Closure to Replant Slope

TRAFFIC ADVISORY - CLEAN RIVERS - POTOMAC RIVER TUNNEL PROJECT

DC Water is in the final stretch of its slope stabilization project along Canal Road NW, a critical project that will pave the way for Potomac River Tunnel construction at this site. Beginning, the week of December 15, 2025, one westbound lane of Canal Road will be closed during daytime, off-peak hours on weekdays and Saturdays to hydroseed the slope.

Latest Blog Post
A helicopter lowers a drill rig to workers on the Potomac River.
DC Water begins drilling in Potomac River to explore options to rehab underwater sewer line
When one of your major sewer lines runs through the Potomac River, a backhoe and trencher won't do. That's why we've got helicopters carrying a 14-ton drill and workers suspended midair over the Potomac.